Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : REBUILDING OF COKE OVEN BATTERY NO-6 (BSP).

Reported Date : 30-SEP-11

MOU Status :

Monthly Report : 7 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
172.780172.78

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
125.726.01.22131.95

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20100/06/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone