Reported Date :
04-FEB-15
|
MOU Status :
Project Under MOU for 2014-2015
|
Monthly Report :
12
/
2014
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
21
|
Total/Pending/Completed Milestone -
20
/
0
/
20
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
10870.17 | 756.95 | 54.68 | 11681.8 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
All new facilities under the integrated process route of BF-BOF-Caster-Plate Mill are in operation. The installed crude steel capacity of the plant has increased from 1.9 million tons per annum (Mtpa) to 4.2 Mtpa.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |