Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : EXPANSION OF ROURKELA STEEL PLANT.

Reported Date : 04-FEB-15

MOU Status : Project Under MOU for 2014-2015

Monthly Report : 12 / 2014

Cost Overrun (%)-   0

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 20 / 0 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11812011812

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10870.17756.9554.6811681.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20130/012/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

All new facilities under the integrated process route of BF-BOF-Caster-Plate Mill are in operation. The installed crude steel capacity of the plant has increased from 1.9 million tons per annum (Mtpa) to 4.2 Mtpa.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone