Reported Date :
19-SEP-14
|
MOU Status :
Not Under MOU for 2014-2015
|
Monthly Report :
7
/
2014
|
Cost Overrun (%)- 70.09
|
Time Overrun (Months)-
46
|
Total/Pending/Completed Milestone -
3
/
0
/
3
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Commissioned and synchronized with Grid on 06th Nov,2013, after obtaining synchronization clearance from APTRANSCO. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |