Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : 330 TPH BOILER-6 AND AUXILIARY SYSTEM.

Reported Date : 19-SEP-14

MOU Status : Not Under MOU for 2014-2015

Monthly Report : 7 / 2014

Cost Overrun (%)-   34.48

Time Overrun (Months)-    42

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
260349.64349.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
259.71.92.12260.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20098/20106/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-OCT-1398Completed

Monthly Status

Background Information

Unit commissioned in June, 2013. Unit is under operation.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone