Sector Name : STEEL.
Agency Name : NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC).
Project Name : 1.2 MTPA PELLET PLANT PROJECT ,DONIMALAI (NMDC).

Reported Date : 21-JUN-16

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 5 / 2016

Cost Overrun (%)-   0

Time Overrun (Months)-    26

Total/Pending/Completed Milestone - 19 / 1 / 18

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5720572

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
451.5800451.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20139/20146/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone