Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : REBUILDING OF BATTERY BLOCK 5A AND RE-CONSTRUCTION OF BATTERY BLOCK 5B.

Reported Date : 23-FEB-16

MOU Status : Project Under MOU for 2015-2016

Monthly Report : 1 / 2016

Cost Overrun (%)-   0

Time Overrun (Months)-    7

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
313.050313.05

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
205.93108.945.04319.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20150/01/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone