Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : CAPTIVE POWER PLANT - 2.

Reported Date : 04-DEC-15

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 10 / 2015

Cost Overrun (%)-   0

Time Overrun (Months)-    22

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6770677

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
509.4123.893.89537.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20130/07/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-SEP-1595Completed

Monthly Status

Background Information

The 120 MW Turbo Generator (TG) along with one Boiler was commissioned by synchronizing with the state grid on 29th July,2015. Second Boiler was also commissioned on 15th Sept, 2015.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone