Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : 3RD CONVERTER AND 4TH CASTER.

Reported Date : 08-FEB-18

MOU Status : Project Under MOU for 2016-2017

Monthly Report : 12 / 2017

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
974.760974.76

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
472.53142.462676.93

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20160/012/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
17-NOV-1796.01Completed

Monthly Status

Background Information

3rd Converter: The 3rd Converter was commissioned on 07th Nov,2016. 4th Caster: 4th Caster was successfully commissioned on 28th Dec,2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone