Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : BLAST FURNACE-2 CATEGORY-1 CAPITAL REPAIRS.

Reported Date : 08-DEC-17

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 10 / 2017

Cost Overrun (%)-   0

Time Overrun (Months)-    27

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
877.730877.73

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
717.1628.921.73747.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20150/010/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
20-JUN-17100Completed

Monthly Status

Background Information

A decision was taken to start BF-2 after stabilization of Sinter Machine-1. Furnace lighted up on 21.10.2017. 1st Tapping was done on 23.10.2017 and Furnace is under stabilization.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone