Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : FORGED WHEEL PLANT.

Reported Date : 31-JAN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2022

Cost Overrun (%)-   24.79

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1682.8502100

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1652.02115.9601767.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20189/20219/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
222222

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-SEP-210Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone