Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : COKE OVEN BATTERY-5.

Reported Date : 07-JAN-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 12 / 2021

Cost Overrun (%)-   0

Time Overrun (Months)-    57

Total/Pending/Completed Milestone - 6 / 1 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
285802858

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1912.67106.0502018.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20179/20229/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
125125

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-SEP-21100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone