Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : REBUILDING OF COKE OVEN BATTERY NO-8 AT BSL.

Reported Date : 01-FEB-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    42

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
262.870262.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
271.133.670274.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20196/202212/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6.880

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-DEC-22100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone