Reported Date :
08-MAR-21
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
2
/
2021
|
Cost Overrun (%)- 4.78
|
Time Overrun (Months)-
27
|
Total/Pending/Completed Milestone -
4
/
0
/
4
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
•Over Head Electrification (OHE) system charged on 09.11.2020.
•Commercial notification for CDY operation obtained from Railways on 24.11.2020.
•12 rakes of Rail dispatches done in Feb,2021.
•The Project is completed and the unit is under operation.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |