Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : RASTRIYA ISPAT NIGAM LIMITED.
Project Name : ADDITIONAL WATER STORAGE RESERVOIR(KBR-II).

Reported Date : 30-SEP-19

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 7 / 2019

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
465.850465.85

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
370.25200390.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20187/20197/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
25-JUN-19100Completed

Monthly Status

Background Information

The unit was commissioned on 24th July,2019 and the Project is completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone