Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : UP GRADATION OF AUTOMATION SYSTEM OF HOT STRIP MILL AT BOKARO STEEL PLANT.

Reported Date : 06-AUG-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 7 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
207.740207.74

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
176.258.760185.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20240/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
87.390

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-MAY-24100Completed

Monthly Status

Background Information

3rd short shut-down taken during 29.02.2024 to 02.03.2024. Trial testing of two stands completed. Further, dismantling of Gauge house started on 29.02.2024. As per plan, 2nd and last major shut-down has been taken from 01.04.2024 to 20.04.2024. For the month of MAR-2024, total manpower of 178 nos. includes 3 nos. of SAIL employees and 175 nos. of contractor manpower.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone