Reported Date :
06-AUG-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
7
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
2
/
0
/
2
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| 3rd short shut-down taken during 29.02.2024 to 02.03.2024. Trial testing of two stands completed. Further, dismantling of Gauge house started on 29.02.2024.
As per plan, 2nd and last major shut-down has been taken from 01.04.2024 to 20.04.2024.
For the month of MAR-2024, total manpower of 178 nos. includes 3 nos. of SAIL employees and 175 nos. of contractor manpower. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |