Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC).
Project Name : CONSTRUCTION OF RESIDENTIAL TOWERS AT BIOM KIRANDUL COMPLEX.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 9 / 4 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
282.44349.75349.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
206.0926.256.65238.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20240/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1110

Ministry Review Date

LatestLastPhysical Progress (%)Status
11-JUN-2581.86Ongoing

Monthly Status

Background Information

Cumulative RCC of 1195 Cu.M, Reinforcement of 90 MT and Aluminium formwork of 5420 Sq.M achieved during the month. Manpower indicated consists of 02 nos. from NMDC, 04 from NBCC and 276 from the Contractor.Construction of Towers in percentage (%): 1. Tower-3A- 59.78% 2. Tower-3B- 37.28% 3. Tower-3C- 19.05% 4. Tower-3D- 21.08% 5. Tower-3E- 59.80% 6. Tower-4A- 9.38% 7. Tower-4B- 11.25% 8. Tower-4C- 7.50% 9. Tower-5- 31.88% Manpower indicated consists of 03 nos. from NMDC, 05 no. from PMC and 354 nos. from package contractor.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks