Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : REPLACEMENT OF REMAINING 04 NOS. OF BATTERY CYCLONES WITH 04 NOS. OF ESPS IN SINTER PLANT-1 AT BSL.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
260.370260.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
19.5323.331.3644.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20260/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1020

Ministry Review Date

LatestLastPhysical Progress (%)Status
12-JUN-2518Ongoing

Monthly Status

Background Information

Electrical panel under installation. For ESP 1, area preparation is under progress. Pre shutdown jobs started, Plan for activities under preparation. Civil Piling work started. Total manpower for the month of JUN-2025 is 49 nos. which includes 1 nos of SAIL employees and 38 of Contractor manpower.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks