Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC).
Project Name : SCREENING PLANT-II, DONIMALAI.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 6 / 6 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1043.6301043.63

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
171.5109.7181.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20260/08/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
21-MAY-2513.61Ongoing

Monthly Status

Background Information

"Cumulative Excavation of 39180 Cu.M & RCC of 1385 Cu.M achieved during the month. The manpower indicated consists of 11 nos. from NMDC, 03 nos. from MN Dastur and 267 nos. from Contractors of different packages.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks