Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : UP-GRADATION OF BLAST FURNACE NO. 3 AT DURGAPUR STEEL PLANT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
758.090758.09

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
035.34035.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20260/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
182.430

Ministry Review Date

LatestLastPhysical Progress (%)Status
12-JUN-252.5Ongoing

Monthly Status

Background Information

Contract signed on 04.10.2024. Design Engineering is in progress. Enabling work started from 18.11.2024. 3D scanning of furnace area in progress. Dismantling of cooling tower, equipment of existing pump house completed. Dismantling of coal tar injection room is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks