Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : REVAMPING OF AIR POLLUTION CONTROL SYSTEMS OF SP-1 AT DURGAPUR STEEL PLANT.

Reported Date : 01-MAY-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
196.40196.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0.190.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20260/05/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
56.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
08-MAY-25.9Ongoing

Monthly Status

Background Information

Contract signed on 17.01.2025. Design Engineering in progress. L2 Schedule submitted.