Project Summary
Project Summary
Sector Name : STEEL.
Agency Name : STEEL AUTHORITY OF INDIA LIMITED (SAIL).
Project Name : THIRD LADLE FURNACE IN SECONDARY REFINERY UNIT AT IISCO STEEL PLANT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
227.960227.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
02.58.032.61

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20260/07/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200

Ministry Review Date

LatestLastPhysical Progress (%)Status
12-JUN-2529Ongoing

Monthly Status

Background Information

Structural dismantling of ARS 2 and 3 have been completed. Design engineering under progress. Equipment ordering under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks