Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BONGAIGAON REFINERY PETROLEUM LIMITED.
Project Name : DIESEL HYDRO TREATMENT PROJECT,BRPL DHALIGAON.

Reported Date : 23-JUL-12

Monthly Report : 5 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1431.911646.391690.13

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1596.8001596.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20090/08/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
850

Ministry Review Date

LatestLastPhysical Progress (%)Status
98.58Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks