Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : ADDL.DEVELOPMENT OF A-1 LAYER,L-III RESERVOIR MHN.

Reported Date : 24-JUL-08

Monthly Report : 3 / 2008

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
910.530910.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
324.26410.410734.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20060/03/2008

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
350350

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-OCT-070Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks