Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : LUBE OIL BASE STOCK QUALITY UPGRADATION AT MUMBAI REFINERY.

Reported Date : 18-NOV-10

Monthly Report : 9 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
638.910301030

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
654.1394.2847.8796.21

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20090/07/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2900

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.97Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks