Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : OFFSHORE GRID INTERCONNECTIVITY PROJECT IN MUMBAI HIGH.

Reported Date : 12-MAY-14

Monthly Report : 3 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
740.020740.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
699.639.59.64739.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20100/02/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
870

Ministry Review Date

LatestLastPhysical Progress (%)Status
28-FEB-14100Completed

Monthly Status

Background Information

PROJECT WAS COMPLETED ON 14.02.2014.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks