Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DEVELOPMENT OF B-22 CLUSTER FIELDS.

Reported Date : 09-SEP-14

Monthly Report : 7 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2323.42920.822920.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1915.450.651916.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20103/20127/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
103.60

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-140Completed

Monthly Status

Background Information

PROJECT IS COMPLETE.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others9/20104/2013PendingImmediate