Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : MSQ UPGRADATION PROJECT AT GUWAHATI REFINERY.

Reported Date : 14-FEB-11

Monthly Report : 12 / 2010

  

   

Total/Pending/Completed Milestone - 28 / 0 / 28

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3720276

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
184.4342.731.88229.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
850

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks