Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : MSQ UPGRADATION PROJECT AT DIGBOI REFINERY.

Reported Date : 14-FEB-11

MOU Status :

Monthly Report : 12 / 2010

Cost Overrun (%)-   0

Time Overrun (Months)-    24132

Total/Pending/Completed Milestone - 27 / 0 / 27

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3560251

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
170.747.754.24222.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
820

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

All units commissioned progressively from Sep’10 to Dec’10* ¿ NSU commissioned on 14.09.10 ¿ RSU on 20.09.10 ¿ NDHT on 27.10.10 ¿ ISOM Unit commissioned on 28.12.10

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <