Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : MSQ UPGRADATION PROJECT AT BARAUNI REFINERY.

Reported Date : 14-FEB-11

Monthly Report : 12 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
149201525

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
795.5303.4914.11113.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20100/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5600

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

MSQ UNITS HAVE BEEN COMMISSIONED.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks