Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : MNW-NF BRIDGE PROJECT.

Reported Date : 17-MAY-12

Monthly Report : 3 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
175.210175.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
58.26109.644.52172.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20092/20120/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
15.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
29-FEB-12100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks