Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DEVELOPMENT OF B-46 CLUSTER FIELD.

Reported Date : 22-AUG-14

Monthly Report : 6 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1436.2101456.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1165.53001165.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20105/20125/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-14100Completed

Monthly Status

Background Information

PROJECTWAS COMPLETED ON 14.05.14.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks