Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : BIJAPUR DADRI-BAWANA PIPE LINE PROJECT.

Reported Date : 09-MAR-11

Monthly Report : 1 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
5595.3143163700

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3179.94146.0703326.01

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/04/20101/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
79217

Ministry Review Date

LatestLastPhysical Progress (%)Status
29-JUN-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks