Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : DAHEJ-VIJAYPUR PIPE LINE PROJECT(PHASE-II).

Reported Date : 13-JAN-12

Monthly Report : 12 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4429.3802370

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2047.59250.0727.942325.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20100/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0269.8

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-DEC-11100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks