Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : COMPRESSOR STATIONS (VIJAYPUR AND JHABUA) PHASE-I AND II.

Reported Date : 20-SEP-11

Monthly Report : 7 / 2011

  

   

Total/Pending/Completed Milestone - 3 / 0 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
15121434975

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
828.4113.734.47846.61

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/201112/20117/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1320

Ministry Review Date

LatestLastPhysical Progress (%)Status
96.8Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks