Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : COMPRESSOR STATIONS (KAILARAS AND CHAINSA).

Reported Date : 30-APR-13

Monthly Report : 2 / 2013

  

   

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11670798

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
706.299.440715.73

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20110/02/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
076

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks