Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : INSTALLATION OF FCCU AT MUMBAI REFINERY.

Reported Date : 25-MAY-11

Monthly Report : 3 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
900.470900.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
565.96185.02149.02900

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20090/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1730

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks