Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PARADIP REFINERY PROJECT.

Reported Date : 06-MAY-16

MOU Status : Not Under MOU for 2015-2016

Monthly Report : 3 / 2016

Cost Overrun (%)-   16.05

Time Overrun (Months)-    39

Total/Pending/Completed Milestone - 100 / 4 / 96

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
297773455534555

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
28733.72566.83127.3731427.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/201211/20132/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
20000

Ministry Review Date

LatestLastPhysical Progress (%)Status
12-APR-1699.1Completed

Monthly Status

Background Information

Dedicated to nation by Honble Prime Minister on 07.02.16

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone