Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : BRANCH PIPELINE FROM KSPL VIRAMGAON TO KANDLA.

Reported Date : 14-MAY-12

MOU Status :

Monthly Report : 3 / 2012

Cost Overrun (%)-   0

Time Overrun (Months)-    -12

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
250349250

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
158.0771.014.43233.51

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20130/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1300

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone