Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : ASSAM RENEWAL PROJECT FOR GROUP A.

Reported Date : 06-MAR-20

Monthly Report : 1 / 2020

  

   

Total/Pending/Completed Milestone - 15 / 0 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2465.1502378.86

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2122.5434.6220.422177.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/201312/201912/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
900

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JAN-20100Completed

Monthly Status

Background Information

Project completed on 31.12.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks