Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : HEERA RECONSTRUCTION.

Reported Date : 17-MAY-12

Monthly Report : 3 / 2012

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
706.70706.7

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
567.05129.474.23700.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20100/03/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
59.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-12100Completed

Monthly Status

Background Information

ALL REVAMPING AND RECONSTRUCTION WORK COMPLETED. PROJECT COMPLETED SUCCESSFULLY ON 31.03.2012.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks