Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : ADDITIONAL GAS PROCESSING UNITS AT URAN.

Reported Date : 07-MAR-14

Monthly Report : 1 / 2014

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1797.350977

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
726.73115.250841.98

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20110/012/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2970

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JAN-14100Completed

Monthly Status

Background Information

PROJECT WAS COMPLETED SUCCESSFULLY ON 14.12.13.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks