Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : ADDITIONAL GAS PROCESSING FACILITY AT HAZIRA.

Reported Date : 30-MAY-13

Monthly Report : 3 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
370.110370.11

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
211.2468.490279.73

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20110/03/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
66.210

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAR-13100Completed

Monthly Status

Background Information

PLANT WAS MECHANICALLY COMPLETED IN SEP.’12. AFTER RECEIVING OISD APPROVAL ON 04.01.13, COMMISSIONING OF THE PLANT WAS TAKEN UP AND WAS SUCCESSFULLY COMPLETED ON 02.03.2013.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks