Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : DIESEL HYDROTREATOR PROJECT AT MUMBAI REFINERY.

Reported Date : 09-SEP-14

Monthly Report : 7 / 2014

  

   

Total/Pending/Completed Milestone - 76 / 0 / 76

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
328421742174

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1881.8934.4101916.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20115/201212/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
600

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks