Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : GURU GOVIND SINGH REFINARY PRODUCTS EVACUATION PROJECT.

Reported Date : 30-JUN-11

MOU Status :

Monthly Report : 4 / 2011

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 16 / 0 / 16

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
605.4605.4510

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
173.08221.2714.55510

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/201012/201012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
160160

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project has been completed in December,2010. After receipt of Products from upcoming GGSR, Project would be commissioned

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone