Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : BINA KOTA PIPE LINE PROJECT.

Reported Date : 07-SEP-10

Monthly Report : 7 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
405.820405.82

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
340.6414.16.13354.93

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20093/20107/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
750

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project has been completed in March 2010

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks