Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : CAPACITY EXP. CUM MODERNISATION PH-II.

Reported Date : 30-AUG-11

Monthly Report : 6 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2591.803941.41

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3231.9520.9712.183265.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20090/012/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5000

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks