Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : SHORT TERM LOW COST MUMBAI REFINERY.

Reported Date : 03-AUG-10

Monthly Report : 5 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
390230390

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
187.45.31.67188.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20100/01/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
330

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

The project has been completed in January 2010 and on-grade production commenced, since February 2010.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks