Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : REFRIGERAPED LPG STORAGE AT JNPT.

Reported Date : 15-MAY-12

Monthly Report : 3 / 2012

  

   

Total/Pending/Completed Milestone - 60 / 0 / 60

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
304.40304.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
226.6335.748.63271

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20100/01/2012

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7045

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks