Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : CONSTRUCTION OF 12 OFFSHORE SUPPLY VESSELS(OSV).

Reported Date : 04-JUL-19

Monthly Report : 5 / 2019

  

   

Total/Pending/Completed Milestone - 3 / 0 / 3

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
736.650571.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00331.47331.47

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20115/20185/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

* The contract expired on 31-05-2018 and was not extended. As per clause 18 of contract the contract deemed expired as no extension was given. After deliberation contract was formally terminated. THE CONTRACT STANDS TERMINATED FROM 23-07-2018. All Bank Guarantees with interest and PBG have been enchased. As on date only 7 out 12 OSVSs are delivered. * The matter is Subjudiced in Hon’ High Court of Bombay.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks