Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : ADDITIONAL DEV. OF D-1 FIELD.

Reported Date : 09-SEP-14

Monthly Report : 7 / 2014

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2163.642331.622331.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2154.8927.4202182.31

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20120/07/2014

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
213.320

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-140Completed

Monthly Status

Background Information

PROJECT IS DECLARED COMPLETE AT THIS STAGE.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others6/20126/2013PendingImmediate